TestRay for Jira DC

Generate Test Execution Weekly Progress Report

Reports can be generated on test execution weekly progress statistics.

Please follow below steps to generate "Test Execution Weekly Progress Report":

  1. Open a Jira project

  2. Click "TestRay Reports" from the left navigation panel

  3. From the list, find "Test Execution Weekly Progress Report"

  4. Click "Test Execution Weekly Progress Report"

  5. Specify from the filter options below and click the "Generate Report" button:

    - Select a JIRA project from "Project" dropdown list
    - Select a Test Plan from "Test Plan" dropdown list (optional)
    - Select a Test Cycle from "Test Cycle" dropdown list (optional)
    - Specify "Executed between"

You can save your selections as an "Report Configuration" to reuse it in the future.

UG96_Test_Execution_Progress_Report_Configuration.png

[Screenshot - UG96_Test_Execution_Progress_Report_Configuration]

UG96_Test_Execution_Progress_Report_Result.png

[Screenshot - UG96_Test_Execution_Progress_Report_Result]